Well Plugging Operations at 181 Robson Road

Share Well Plugging Operations at 181 Robson Road on Facebook Share Well Plugging Operations at 181 Robson Road on Twitter Share Well Plugging Operations at 181 Robson Road on Linkedin Email Well Plugging Operations at 181 Robson Road link

The Ministry of Natural Resources has hired a qualified contractor, Eastern Oilfield Services, to carry out well plugging operations at 181 Robson Road under the Abandoned Works Program.

  • Start Date: August 18, 2025, with other supporting operations to begin as early as August 6.
  • Project location: 181 Robson Road
  • Estimated Duration: 4 to 6 weeks
  • Contractor: Eastern Oilfield Services on behalf of the province

This work has been carefully planned with public safety as a top priority. We kindly ask residents and visitors to avoid accessing the area unnecessarily while operations are in progress.

For more information about the project, contact the Petroleum Operations Section at 519-873-4634 or email gasandoilwells@ontario.ca. For urgent public safety concerns during the operation, please contact 911.

The ministry appreciates your cooperation and understanding.

The Ministry of Natural Resources has hired a qualified contractor, Eastern Oilfield Services, to carry out well plugging operations at 181 Robson Road under the Abandoned Works Program.

  • Start Date: August 18, 2025, with other supporting operations to begin as early as August 6.
  • Project location: 181 Robson Road
  • Estimated Duration: 4 to 6 weeks
  • Contractor: Eastern Oilfield Services on behalf of the province

This work has been carefully planned with public safety as a top priority. We kindly ask residents and visitors to avoid accessing the area unnecessarily while operations are in progress.

For more information about the project, contact the Petroleum Operations Section at 519-873-4634 or email gasandoilwells@ontario.ca. For urgent public safety concerns during the operation, please contact 911.

The ministry appreciates your cooperation and understanding.

  • Project Update # 1 - Start of Plugging

    Share Project Update # 1 - Start of Plugging on Facebook Share Project Update # 1 - Start of Plugging on Twitter Share Project Update # 1 - Start of Plugging on Linkedin Email Project Update # 1 - Start of Plugging link

    Preparation of the site for the upcoming well plugging operations is now complete. Equipment mobilization is currently underway, with plugging activities scheduled to begin on Monday, September 8, 2025.

    Members of the public are reminded to stay clear of the site during this period due to increased operational activity.

    A follow-up update will be issued once plugging operations are complete.